I have a few questions for the more experienced BH operators out there. I have the BX25 with the BT602CA BH. I'm getting pretty good at trenching (IMO LoL) and have been doing quite a few trenching jobs. Here are my main questions...
1) when starting a trench say from a garage to the house, how do you guys finish the trench when you run out of room by the house so you can keep the trench straight? I find it hard to trench on angles because you don't get a nice straight line (important for laying pipe)
2) Friend told me about carrying couple of sheets of 3/4" 4x8 plywood and lay it over the trench, position tractor on and over it I guess and keep trenching.
I've had a few where I started at both ends of the trench (house first then move to garage) and had a roughly 4' spot in the middle to join up. It was sickening getting off the tractor to move it around to trench it together...plus it looked crappy IMO
So if you guys have some suggestions on how to join up a trench and how to use the plywood, I would appreciate it thanks!
1) when starting a trench say from a garage to the house, how do you guys finish the trench when you run out of room by the house so you can keep the trench straight? I find it hard to trench on angles because you don't get a nice straight line (important for laying pipe)
2) Friend told me about carrying couple of sheets of 3/4" 4x8 plywood and lay it over the trench, position tractor on and over it I guess and keep trenching.
I've had a few where I started at both ends of the trench (house first then move to garage) and had a roughly 4' spot in the middle to join up. It was sickening getting off the tractor to move it around to trench it together...plus it looked crappy IMO
So if you guys have some suggestions on how to join up a trench and how to use the plywood, I would appreciate it thanks!